### Cylindrical Foundation & Sonotube Concrete Metrology (ACI 318) Cylindrical post footing volume follows the geometric cylinder formula: - **$\text{Radius (ft)} = \frac{\text{Diameter.

Reviewed by Sagar Sageer · Associate Engineer
Last updated:
Editorial Guidelines

⚙ Input Values

📊 Results

Total Concrete (yd³)
0.36
yd³
Total Volume (cu ft)
9.6
cu ft
Metric Volume (m³)
0.27
m³
80 lb Pre-Mix Bags
16
bags
60 lb Pre-Mix Bags
22
bags
Estimated Material Cost
51.55
$
Total Cured Mass (lbs)
1,392
lbs
✦ Foundation Engineering Summary
Cylindrical Footing Foundation (4 tubes @ 10" dia × 4.0 ft depth): Net 8.73 cu ft. With 10% waste: 9.60 cu ft (0.36 yd³ / 0.27 m³). Requires 16 × 80 lb bags OR 22 × 60 lb bags. Estimated ready-mix cost: $51.55 (Mass: 1,392 lbs [631 kg]).
Embed on Your Website

Copy and paste this code into your website.

<iframe src="https://calcusolve.com/calculator/concrete-estimator-tube?embed=true" width="100%" height="600" frameborder="0" loading="lazy" title="Concrete Estimator - Sonotube & Post Footings"></iframe>

📐 Formula

Cylindrical Volume = PI * r^2 * h
Pre-mix bag yields: 80 lb = 0.60 cu ft, 60 lb = 0.45 cu ft

💡 Practical Example

✅

Pouring a single 12" diameter × 4 ft deep Sonotube pier requires 3.14 cu ft of concrete (6 bags of 80 lb Quikrete).

📖 About Concrete Estimator - Sonotube & Post Footings

Cylindrical Foundation & Sonotube Concrete Metrology (ACI 318)

Cylindrical post footing volume follows the geometric cylinder formula:

  • Radius (ft) = Diameter (in)24
  • Volume (cu ft) = π × r^2 × Depth (ft) × Number of Tubes
  • Cubic Yards (yd^3) = Volume (cu ft)27

Pre-Mix Concrete Bag Yields

  • 80 lb Bag: Yields approximately 0.60 cu ft (45 bags per cubic yard)
  • 60 lb Bag: Yields approximately 0.45 cu ft (60 bags per cubic yard)
  • 50 lb Fast-Setting Bag: Yields approximately 0.375 cu ft (72 bags per cubic yard)

Standard Sonotube Sizing Chart (4-Foot Frost Depth Pier)

  • 8" Tube × 4 ft: = 1.40 cu ft = 0.052 yd^3 = 3 bags (80 lb)
  • 10" Tube × 4 ft: = 2.18 cu ft = 0.081 yd^3 = 4 bags (80 lb)
  • 12" Tube × 4 ft: = 3.14 cu ft = 0.116 yd^3 = 6 bags (80 lb)
  • 16" Tube × 4 ft: = 5.59 cu ft = 0.207 yd^3 = 10 bags (80 lb)
  • 18" Tube × 4 ft: = 7.07 cu ft = 0.262 yd^3 = 12 bags (80 lb)
  • 24" Tube × 4 ft: = 12.57 cu ft = 0.465 yd^3 = 21 bags (80 lb)

How to Use This Calculator

Enter your Tube Diameter (Inches) (e.g. 10), Tube Depth / Height (Feet) (e.g. 4), Tube Depth (Inches) (e.g. 0), Number of Tubes / Piers (e.g. 4), Waste & Spillage Allowance (%) — choose from 0% (Exact Geometric Volume), 5% (Smooth Cardboard Tube Forms), 10% (Recommended Sonotubes & Overfill), and Concrete Price per Cu Yard () (e.g. 145.00). Measure twice before entering dimensions — small measurement errors scale up significantly in material estimates.

The Formula

Cylindrical Volume = PI r^2 h

Pre-mix bag yields: 80 lb = 0.60 cu ft, 60 lb = 0.45 cu ft

Worked Example

Pouring a single 12" diameter × 4 ft deep Sonotube pier requires 3.14 cu ft of concrete (6 bags of 80 lb Quikrete).

Understanding Your Result

Always add a 10–15% waste factor to concrete volume estimates for normal pours, and 15–20% for irregular forms or slabs with cutouts. Standard ready-mix concrete is ordered in cubic yards (1 cubic yard = 27 cubic feet). Minimum slab thickness recommendations: driveways 4 inches, garage floors 4–6 inches, structural slabs per engineer specification. Over-ordering concrete is generally preferable to under-ordering — a short pour creates a cold joint that weakens the structure.

💡 Methodological Standards & Calculation Accuracy

  • All calculations are performed client-side in your browser using verified, standards-compliant mathematical algorithms.
  • Results are provided for educational and informational analysis; verify critical applications with certified domain specialists.
  • Ensure input values are entered in consistent units matching the selector options to guarantee accurate outputs.
  • Periodic recalibration is recommended whenever baseline assumptions, operating parameters, or external conditions change.

Results are for informational and educational purposes only. Always verify critical decisions with a qualified professional.

❓ Frequently Asked Questions

How many 80 lb bags of concrete for a 10 inch Sonotube 4 feet deep?

A 10-inch diameter tube 4 feet deep requires approximately 2.18 cubic feet of concrete, which equals 4 bags of 80 lb concrete mix (or 5 bags of 60 lb mix).

How many 80 lb bags are in a cubic yard of concrete?

There are exactly 45 bags of 80 lb concrete in one cubic yard.

How do you calculate concrete for a cylindrical tube?

Divide diameter in inches by 24 to get radius in feet, square the radius, multiply by 3.14159, then multiply by the depth in feet.

How many bags of concrete for a 12 inch Sonotube?

A 12-inch Sonotube requires approximately 0.785 cubic feet per foot of depth (e.g., a 4-foot deep tube requires 3.14 cu ft or 6 bags of 80 lb concrete).

Why should I add 10% waste for Sonotube concrete?

Adding 10% accounts for spillage during pouring, slight expansion of cardboard tube walls under wet concrete hydrostatic pressure, and uneven hole bottoms.